£7.5 million worth of CIF bids secured in 2019

Hookway helped over 30 academies secure a combined total of more than £7.5 million in Condition Improvement Fund (CIF) funding for 2019. The individual funding was approved in April and the projects then needed to be planned, implemented and completed by the beginning of September in time for the start of the new academic year.

From boiler replacements to school building refurbishments

The various CIF Funding projects were approved to address a variety of different issues such as safeguarding, building compliance and poor building conditions. Work included complete roof repairs, constructing a secure entrance lobby, boundary wall repairs, washroom refurbishments, removal of an asbestos roof, boiler replacements and alterations to provide additional classroom space.

Ensuring quality and timeliness of delivery

Projects took between 5-12 weeks to complete depending on the scale of the work. Our team has worked tirelessly throughout to ensure that every aspect of the work was completed to an extremely high standard, delivered on deadline and that the outcome met with our clients’ approval. 

We completed a number of projects for Royal Wotton Bassett Academy Trust. Jon Stewart, the Academy’s business manager said;

“Hookway have been fantastic for us, they have prepared all of our bids and CIF has made huge difference to our buildings over recent years.

“This year we had two bids totalling over a million pounds for Lawn Manor. Our new boilers and plant, and new roof projects, have gone completely smoothly, safely and within budget”.

Project examples include:  

SchoolProjectContract ValueContract Duration
St Adlhelms Primary, DoultingSafeguarding Entrance Extension£80,0008 weeks (2 weeks Easter Holidays, 6 weeks term time)
Oakhill Primary School, RadstockInternal Alterations to provide additional classroom£56,0009 weeks (3 weeks term time, 6 weeks Summer Holidays)
Combe St Nicholas CE Primary, ChardRoof and boundary wall repairs£50,00010 weeks (6 weeks summer holidays, 2 weeks term time and 2 weeks Easter 2020)
St Gildas Catholic Primary, YeovilToilet refurbishment and damp eradication£58,0007 weeks
Easton Primary Academy, Bristol: Pipework and Heater Renewal£420,00012 weeks (6 weeks full time and 6 weeks evenings and weekends)
Sexey’s Secondary Academy, BrutonAsbestos Roof renewal£180,0005 weeks
Pewsey Vale School, WiltshireBoiler Replacement£300,00010 weeks
Roundwood Park School, HarpendenWashroom Refurbishments£250,0006 weeks

If you need help with securing condition improvement funding for 2020 Hookway can help. We can also carry out a Prioritised Maintenance Survey to assess the condition and performance of your building and identify areas that require improvement.

For more information call Greg or Anna on 0117 955 4545 or email your enquiry and we will get back to you.

Looking for proven expertise on your next project?

Our case studies demonstrate how we deliver clarity, control and successful outcomes. Get in touch to see how we can support your project from concept to completion