This websites use cookies. By continuing to browse the site you are agreeing to our use of cookies. For more details about cookies and how to manage them, see our cookie policy.

Sector: Commercial
Service: Cost Consultancy | Principal Designers

Achieving Excellence through Collaboration  

Hookway was appointed as Cost Consultants and CDM Co-Ordinators to review the feasibility of refurbishing an existing factory unit for a large industrial manufacturer. After various options were reviewed the decision was made to demolish the existing building and provide a new build facility. 

The challenge

Hookway reviewed all the available brief information and constraints, along with other design team members and the client, and a procurement route was agreed that would help achieve the requirements with the risk to the client reduced as much as possible.

The works were let on a JCT CE form of contract, on an open book basis with target cost, to allow for maximum collaboration between the parties and a start on site prior to the completion of the design (due to tight programme issues with the ultimate customer) . The building was built to BREEAM Excellent standards.

Hookway, along with the design team, also ensured that thorough investigation was undertaken prior to works being fully designed or tendered. The site contained suspected unexploded bombs, asbestos within the building and ground and highly toxic chemicals from previous industrial processes in addition the the environmental issues of being located adjacent the sea. The surrounding buildings and factory units on the high security site were also required to remain operational at all times.

With the potential risks identified a detailed risk allocation schedule was produced and agreed with all parties so clear ownership of risk was understood.

Detailed processes, method statements and watching briefs were then agreed, implemented and monitored to ensure all works were carried out in a safe way.

The building contains a huge amount of plant and equipment and so the majority of the maintainable items were placed at high level with dedicated walkways and screening to ensure all can be maintained in a safe way and also with minimal disruption to the manufacturing process.

The team involved on the project, to include Hookway, were shortlisted for the regional Constructing Excellence awards 2015 in the category of Collaborative Working; the key objective of BIM. The project was additionally shortlisted for the regional Constructing Excellence awards 2015 in the category of Health and Safety; the second time a team involving Hookway has been nominated.

The solution

Hookway reviewed all the available brief information and constrains, along with other design team members and the client, and a procurement route was agreed that would help achieve the requirements with the risk to the client reduced as much as possible.

The works were let on a JCT CE form of contract, on an open book basis with target cost, to allow for maximum collaboration between the parties and a start on site prior to the completion of the design (due to tight programme issues with the ultimate customer) . The building was built to BREEAM Excellent standards. The team involved on the project, to include Hookway , were shortlisted for the Constructing Excellence awards 2015 in the category of Collaborative Working; the key objective of BIM.

Hookway carried out full cost management and CDM duties from inception to completion to include, inter alia, option appraisals, cost planning, life cycle costing, two stage tender documentation, tender reporting, contract document preparation, change and cost management, undertaking valuations, claim and contractual advice to the client and final account negotiations.

The result

Despite almost 1,200 variations and a constantly evolving brief the £26.5m project was delivered to the client by the revised completion date and within the anticipated revised budget.

The works undertaken have cleaned up the contamination to the satisfaction of the relevant agencies and despite hundreds of operatives working on the project for several years only a handful of very minor health and safety issues occurred. The facility is considered to be an exemplar for the type of production undertaken.

Related case studies

Office Development

Sensitive design helps meet stringent planning requirements for new commercial premises to house d&b audiotechnik UK headquarters in the Cotswolds

Read full case study

DVSA

Hookway was part of the team who won the Constructing Excellence Integration and Collaborative Working Award in relation to the work done on DVSA projects.

Read full case study

Residential pool

A private client approached Hookway to assist with providing early budget advice on a new build swimming pool within the garden of their home.

Read full case study

Testimonial

“After a fantastic refurbishment of our Grade II* listed building roof last year, Hookway has excellently project managed a complete transformation of our asbestos roofs. ”

“We had to prepare and construct additional facilities, within two terms, to accommodate a child with severe and profound needs. The initial task seemed totally overwhelming, however Hookway took on the role of project managing the nearly £100,000 extension and enabled school life to continue with very few changes. ”

“Hookway have worked in collaboration with us to deliver this transformation project and have provided regular clear communication throughout which has helped with the smooth running of the project. The project team have all played a vital role in this year-long programme and we’re delighted the project has finished on time and on budget.”