Sector: Education
Service: Building Surveying | Project Management

Holy Trinity School 

Faced with a shortage in early years pupil places in Somerset, the local authority engaged Hookway to design and project manage the construction of a new four classroom block.  A Victorian town centre school was chosen as the new build site. Having recently completed a successful new extension to create a new assembly hall at the school we were asked to provide a modern teaching block that would fit comfortably within the existing topography.

The challenge

Following our options appraisal the site of a former swimming pool opposite the main school entrance was chosen as the build site. Highly aware of effect that poor school design can have on teaching and learning the stakeholders had very firm ideas on performance requirements.

The solution

Despite the restricted site area and very close proximity to the existing school entrance the works were a great success. Although apprehensive before the start, school staff and pupils enjoyed the whole process. They were encouraged to take part in the design and kept a keen interest during construction.

The result

The design is popular with pupils and staff alike and the local authority are very pleased with the whole experience especially as time and budget constraints were not exceeded. Each classroom has easy access to covered play and the integration between internal learning and external play has been a success. Hookway still enjoys a good working relationship with the school and act as their maintenance surveyors.

“The whole project has been a complete success from start to finish. Hookway and the builders (HBC) were a pleasure to deal with and the project management was highly professional. It has been open for over a year and teachers and pupils are still excited about the new building it is so well designed in terms of light, space and ventilation that it is a joy to work in. The projecting roof at each end creates fantastic covered play space.” Nigel Bright - Head Teacher

Related case studies

CIF support Ashill primary

Over the last few years Hookway has undertaken CIF bid applications for Ashill Primary school and helped deliver a number of successful projects.

Read full case study

St. Peter's High School

Hookway worked with contractors, Lancer Scott, to provide a complete internal re-modelling and refurbishment of the Sixth Form Block of St. Peter's High School Sixth Form Centre.

Read full case study

CIF 2019 - project round up

Hookway's surveyors worked on numerous CIF projects for schools and academies in 2019, ensuring that all work was completed in time for the start of a new academic year.

Read full case study

Testimonial

“After a fantastic refurbishment of our Grade II* listed building roof last year, Hookway has excellently project managed a complete transformation of our asbestos roofs. ”

“I lose count of the amount of positive comments we receive from visitors on how great the new build looks and it really fits in well with the existing building.”

“Hookway has been vital in the process of applying for this funding. We handed them responsibility and they delivered a concise and detailed package of information which included everything required to submit to Salix. They made it easy and took it out of our hands. We can happily say that Hookway was crucial to us being successful and we look forward to working with them on the 2nd phase of application. ”